- Request for Proposal (RFP) Issued by Owner (Issue by Procurement)
- PreProposal Meeting
- Preliminary Proposal (Detailed line item proposal by JOC contractor using approved current unit price book. Contractor submit proposal to owner with X days of site visit – example: –5 Days: $50k & Under–10 Days: $50k -$100k –15 Days: $100k & Over)
- Negotiation of Proposal
- Job Order Issued
- Pre-Construction Meeting
- Pay Applications
- Regular Owner Inspections
- Punch List(if needed)
- Final Inspection