Programmatic LEAN Job Order Contracting

LEAN Job Order Contracting, as represented by the 4BT OpenJOC(TM) Framework, is a programmatic methodology applied to all construction projects and work orders.

Typically all individual  construction projects have been considered to be unique, with each requiring its own approach, means, and methods.  This is a fundamentally flawed perspective that has significantly contributed to rampant historical economic and environmental waste across the AECOO sector (AECOO – Architecture, Engineering, Construction, Owner, Operator).

For example, the Project Management Institute (PMI) defines a project as follows; “a project is a temporary endeavor. undertaken to create a unique product or service”.   Certainly each construction project has a beginning and an end, however, unless they are all addressed in standardized, professional, and robust manner and associated workflows and a common data environment.  While there are certain unique elements to each construction projects, the granular tasks for virtually any construction project can be defined in advance and stored in a database.   This database, also referred to a detailed unit price book (UPB), or a construction task catalogue, includes the following information for each task:

  1. A description of the construction/repair/renovation/demolition task in plain English.
  2. A unit of measure for the task (each, square foot, cubic yard, etc.)
  3. Associated detailed costs for required labor, material, and equipment to complete the task per the unit of measure, and a total cost for the same.

Using a UPB enables any construction project to be represented in standardized terms which all involved parties can understand.  A UPB solves several major issues that have traditionally faced real property owners, architects, and builders.  First, a robust, detailed scope of work can be easily created and communicated and understood by all parties.  A poorly defined and/or poorly communicated scope of work is responsible for the majority of change orders and cost overruns encountered.   Secondly, a locally researched UPB provides the highest possible certainty with respect to costs.  Furthermore, the discrete elements of a UPB can be then organized into an appropriate work schedule.

A locally researched UPB is one of several key elements of Programmatic LEAN Job Order Contracting.  (Note: a “national average” cost database with/without location factors and “historical costs”, as well as lump sum cost from contractors or subcontractors do no provide requisite cost visibility, transparency, or cost management.)

Holistically, Programmatic LEAN Job Order Contracting is a performance improvement environment, consisting of proven processes, tools, data sources, and techniques. It is a structured  method  of eliminating  waste from throughout the
“project” life-cycle, from conceptualization, through integrated planning, procurement, and execution. Value management for all participants and stakeholders is a key focus that is achieved through everyone having a clear understanding of requirements on an early and ongoing basis and enhanced team dynamics.

Furthermore Programmatic LEAN Job Order Contracting doesn’t require pubic sectors to pay a percentage of JOC total annual construction for access to world class JOC tools, cost data, and support services, saving owners up to 10x+ in JOC administration fees.

Programmatic LEAN Job Order Contracting

Learn more?

Contact Us
First
Last

Variability is an inherent characteristic of construction.   The lack of a robust programmatic process-centric approach causes instability in performance of construction processes causing negative fluctuations of work and poor information flow.

Phases: Conceptualization-Planning-Procurement-Execution-Closeout

Primary Failure Causes:

  1. Lack of management’s leadership, commitment/ involvement/support
  2. Poor allocation of scarce resources
  3. Communications among various participants and stakeholders
  4. Team configuration and structure
  5. Social cohesion in the team  and organizational culture

Programmatic Lean Job Order Contracting

References:

Alarcón, L. F. (1997). “Lean Construction”. New York, Taylor & Francis.
Alarcón, L. F., and D. B. Ashley (1999). “Playing Games: Evaluating the Impact of Lean Production
Strategies on Project Cost and Schedule”. 7th Annual Conference of the International Group
for Lean Construction, IGLC-7, 263-274.
Alarcón, L. F., S. Diethelm, O. Rojo, and R. Calderon (2005). “Assessing the Impacts of
Implementing Lean Construction”. the 13th Annual Conference of the International Group for
Lean Construction, Sidney, Australia, 387-393.
AlSehaimi, A., L. Koskela, and P. Tzortzopoulos (2012). “The Need for Alternative Research
Approaches in Construction Management: The Case of Delay Studies.” Journal of
Management in Engineering.
Alsehaimi, A. O., P. Tzortzopoulos, and L. Koskela (2009). “Last Planner System: Experiences from
Pilot Implementation in the Middle East, 53-65.
Ballard, G., and G. Howell (1994). “Implementing Lean Construction: Stabilizing Workflow”. the 2nd
Annual Conference of International Group for Lean Construction, Santiago, Chile, 105-114.
Ballard, G., and G. Howell (1995). “Toward Construction JIT”. Lean Construction. L. Alarcón. New
York, Taylor & Francis: 291-300.
Ballard, G., and G. Howell (1997). “Implementing Lean Construction: Improving Downstream
Performance”. Lean Construction. L. Alarcón. Rotterdam, Netherlands, A.A. Balkema
Publishers: 111-125.
Ballard, G., and G. Howell (1998). “Shielding Production: Essential Step in Production Control.”
Journal of Construction Engineering and Management 124(1): 11-17.
Ballard, G., L. Koskela, G. A. Howell, and I. D. Tommelein (2005). “Discussion of “Improving Labor
Flow Reliability for Better Productivity as Lean Construction Principle” by H. Randolph
Thomas, Michael J. Horman, R. Edward Minchin Jr., and Dong Chen.” Journal of
Construction Engineering and Management 131(5): 615-616.
Ballard, H. G. (2000). “The Last Planner System of Production Control”. Ph.D., the University of
Birmingham.
Building a Better New Zealand (2013). The Research Strategy for the Building and Construction
Industry.
Building Research Association of New Zealand (2013). Construction Sector Productivity – the
Devil’s in the Detail. Productivity Hub conference.
Construction Industry Council (2006). Nzcic Research Agenda.
Construction Industry Institute (1986). Constructability: A Primer. Texas, USA, Construction Industry
Institute Austin.
Conte, A. S. I. (1998). “Last Planner, Look Ahead, Ppc: A Driver to the Site Operations”. the 6th
Annual Conference of the International Group for Lean Construction (IGLC-6), Guarujá,
Brazil, 1.
Davis, N. (2007). Construction Sector Productivity: Scoping Report. Martin Jenkins for Department
of Building and Housing, Wellington, New Zealand.
Davis, N. (2008). Productivity in the Building and Construction Sector: Summary Report. Martin
Jenkins for Department of Building and Housing, Wellington, New Zealand.
Egan, J. (1998). “The Report of the Construction Task Force to the Deputy Prime Minister, John
Prescott, on the Scope for Improving the Quality and Efficiency of Uk Construction.” The
Department of the Environment, Transport and the Regions.
Erdmann, T. P., H. Boessenkool, L. Hogewoning, and R. J. M. M. Does (2012). “Quality Quandaries:
Reducing Work in Process at an Emergency Assistance Center.” Quality Engineering 25(1):
78-84.
Garvin, D. A. (1988). “Managing Quality: The Strategic and Competitive Edge”. New York, Free
Press.
González, V., and L. F. Alarcón (2010). “Uncertainty Management in Repetitive Projects Using WIP
Buffers”. Germany, Lambert Academic Publishing.
González, V., L. F. Alarcón, S. Maturana, and J. A. Bustamante (2011). “Site Management of Workin-Process Buffers to Enhance Project Performance Using the Reliable Commitment Model:
Case Study.” Journal of Construction Engineering and Management 137(9): 707-715.
González, V., L. F. Alarcón, S. Maturana, F. Mundaca, and J. Bustamante (2010). “Improving
Planning Reliability and Project Performance Using the Reliable Commitment Model.”
Journal of Construction Engineering and Management 136(10): 1129-1139.
González, V., L. F. Alarcón, and K. Molenaar (2009). “Multiobjective Design of Work-in-Process
Buffer for Scheduling Repetitive Building Projects.” Automation in Construction 18(2): 95-
108.
González, V., L. F. Alarcón, and F. Mundaca (2008). “Investigating the Relationship between
Planning Reliability and Project Performance.” Production Planning and Control 19(5): 461-
474.
González, V., L. F. Alarcón, and T. W. Yiu (2013). “Integrated Methodology to Design and Manage
Work-in-Process Buffers in Repetitive Building Projects.” Journal of the Operational
Research Society 64(8): 1182–1193.
González, V., L. Rischmoller, and L. F. Alarcón (2004). “Design of Buffers in Repetitive Projects:
Using Production Management Theory and It Tools”. 4th International Postgraduate Research
Conference, Manchester, U.K., University of Salford.
Hall, R. W. (1983). “Zero Inventories Homewood”. Homewood, Illinois, USA, Dow Jones-Irwin.
Hopp, W. J., N. Pati, and P. C. Jones (1989). “Optimal Inventory Control in a Production Flow
System with Failures.” International Journal of Production Research 27(8): 1367-1384.
Hopp, W. J., and M. L. Spearman (2008). “Factory Physics”. New York, USA, McGraw-Hill, 720.
Horman, M. J. (2001). “Modeling the Effects of Lean Capacity Strategies on Project Performance”.
9th Annual Conference of the International Group for Lean Construction, Kent Ridge
Crescent, Singapore.
Hosseini, S. A. A., A. Nikakhtar, and P. Ghoddousi (2012). “Flow Production of Construction
Processes through Implementing Lean Construction Principles and Simulation.”
Howell, G., and G. Ballard (1994). “Implementing Lean Construction: Reducing Inflow Variation.”
Lean construction.
Howell, G., A. Laufer, and G. Ballard (1993). “Interaction between Subcycles: One Key to Improved
Methods.” Journal of Construction Engineering and Management 119(4): 714-728.
Howell, G. A. (1999). “What Is Lean Construction”. 7th Annual Conference of the International
Group for Lean Construction (IGLC-7 ), Berkeley, California, USA.
Jarkas, A. M., and C. G. Bitar (2011). “Factors Affecting Construction Labor Productivity in Kuwait.”
Journal of Construction Engineering and Management 138(7): 811-820.
Junior, J., A. Scola, and A. Conte (1998). “Last Planner as a Site Operations Tool”. the 6th Annual
Conference of the International Group for Lean Construction (IGLC-6 ), Guarujá, Brazil.
Koo, K.-J., S.-K. Kim, and H. K. Park (2011). “A Simulation Approach for a Periodic Pcr Buffer
Allocation Strategy in Organizational Program Management.” Automation in Construction
20(8): 1020-1029.
Koskela, L. (2000). “An Exploration Towards a Production Theory and Its Application to
Construction “. Ph.D., Technical Research Centre of Finland, Espoo.
Koskela, L., R. Stratton, and A. Koskenvesa (2010). “Last Planner and Critical Chain in Construction
Management: Comparative Analysis, National Building Research Institute, Technion-Israel
Institute of Technology, 538-547.
Koskenvesa, A., and L. Koskela (2005). “Introducing Last Planner-Finnish Experiences, 95-107.
National Research Council (1980). “A National Strategy for Improving Productivity in Building and
Construction: Proceedings of the Building Research Advisory Board’s 1979 Building Futures
Forum”. Washington, USA, National Academy of Sciences.
O’Mahony, M., and B. Van Ark (2003). “Eu Productivity and Competitiveness: An Industry
Perspective: Can Europe Resume the Catching-up Process?”, Office for Official Publications
of the European Communities Luxembourg.
Page, I. C. (2010). Construction Industry Productivity, Study Report 219. Building Research
Association of New Zealand, Wellington.
Page, I. C. (2011). Value of Time Saving in New Housing, Study Report 259. Building Research
Association of New Zealand, Wellington.
Page, I. C., and M. D. Curtis (2011). Firm Productivity Variations, Study Report 254. Building
Research Association of New Zealand, Wellington.
Page, I. C., and M. D. Curtis (2012). Building Industry Performance Measures, Study Report 267.
Building Research Association of New Zealand, Wellington.
Park, M., and F. Peña-Mora (2004). “Reliability Buffering for Construction Projects.” Journal of
Construction Engineering and Management 130(5): 626-637.
Productivity Partnership – Action Plan (2012). Research Action Plan.
Productivity Partnership – Roadmap (2012). Productivity Roadmap.
PWC (2011). Valuing the Role of Construction in the New Zealandeconomy. A report to the
Construction Strategy Group.
Schreyer, P., and O. S. Directorate (2001). “Measuring Productivity: Measurement of Aggregate and
Industry-Level Productivity Growth: Oecd Manual”, Organisation for Economic Co-operation
and Development.
Slack, N., S. Chambers, and R. Johnston (2010). “Operations Management”. Essex, England,
Financial Times/ Prentice Hall.
Thomas, H., M. Horman, U. de Souza, and I. Zavřski (2002). “Reducing Variability to Improve
Performance as a Lean Construction Principle.” Journal of Construction Engineering and
Management 128(2): 144-154.
Thomas, H. R., M. J. Horman, R. E. Minchin Jr, and D. Chen (2003). “Improving Labor Flow
Reliability for Better Productivity as Lean Construction Principle.” Journal of Construction
Engineering and Management 129(3): 251-261.
Tommelein, I. D., D. R. Riley, and G. A. Howell (1999). “Parade Game: Impact of Work Flow
Variability on Trade Performance.” Journal of Construction Engineering and Management
125(5): 304-310.
Williamson, H. M. (2012). Productivity Roadmap.
Womack, J. P., and D. T. Jones (1996). “Beyond Toyota: How to Root out Waste and Pursue
Perfection.” Harvard business review 74: 140-172.
Womack, J. P., and D. T. Jones (2003). “Lean Thinking: Banish Waste and Create Wealth in Your
Corporation, Revised and Updated”. New York, USA, Free Press.